On the Mediterranean coast at El Dabaa, east of Marsa Matrouh, a dream Egypt waited half a century for is coming true: its first nuclear power plant. It is one of the largest projects in Matrouh Governorate’s history.
The plant in numbers
- Reactors: four VVER-1200 units, advanced third-generation pressurised water reactors.
- Total capacity: about 4,800 MW (1,200 MW per unit).
- Partner: Russia’s Rosatom.
- Location: on the El Dabaa coast, about 170 km west of Alexandria.
A long journey
- 1983: El Dabaa was first chosen as the site for a nuclear plant.
- November 2015: the intergovernmental agreement with Russia was signed.
- December 2017: the contracts to begin construction were signed.
- 20 July 2022: first concrete was poured for the base of Unit 1.
- November 2022: construction of Unit 2 began.
- May 2023: construction of Unit 3 began.
- January 2024: construction of Unit 4 began.
- 21 October 2025: the reactor pressure vessel for Unit 1 arrived from Russia at the dedicated El Dabaa port.
- 19 November 2025: the reactor pressure vessel was installed in Unit 1, and the nuclear fuel purchase order was signed.
- 2026: manufacture of key equipment for Unit 1 was completed, including the turbines, pressuriser and steam generators, and the plant received a permit to build a spent fuel storage facility.
- October 2026: the Nuclear Power Plants Authority checked the readiness of the on-site nuclear fuel store and receiving buildings.
What comes next?
- First half of 2027: the first shipment of nuclear fuel arrives and is loaded into the first reactor.
- November 2027: commissioning tests of Unit 1 begin.
- End of 2028: Unit 1 produces its first electricity, at 1,200 MW.
- By 2030: the other three units enter service one after another.
Financing
The project is estimated at about US$28.5 billion, mostly financed by a US$25 billion Russian loan repaid over many years.
What will the plant provide?
- About 10% of Egypt’s electricity once all four units are running.
- Diversified energy sources beyond gas and oil.
- Power for an adjacent desalination plant.
- Thousands of jobs during construction and operation.
The plant and visitors
The plant is a closed strategic facility and cannot be visited, but you pass near its area on the coastal road between El Alamein and Marsa Matrouh. For El Dabaa town itself and its beaches, read the city guide on the blog.
Frequently asked questions
How many reactors does El Dabaa have?
Four VVER-1200 reactors with a combined capacity of about 4,800 MW.
When did construction of El Dabaa begin?
First concrete for Unit 1 was poured on 20 July 2022.
When will El Dabaa start operating?
Unit 1 is expected to produce electricity at the end of 2028, after fuel loading in 2027, with all four units operating by 2030.